 |
|
 |
| |
 |
|
|
|
|
| |

|
|
| |
 |
CRC-Evans custom-designs and installs equipment systems
for both permanent and portable pipe-coating plants.
Our systems are designed for all types of pipe cleaning and coating
processes – both external and internal. We also design and
install all levels of control systems, from simple levers to sophisticated
computer controls. And we maintain close relationships with coating
material manufacturers, to bring you the latest technology
and advanced coating techniques. |
|
|
|
|
|
| |
 |
|
| |
The Joint Coating System is used
to coat selected areas of the pipeline. These areas are usually exposed
areas of butted joints, or rework of damaged coating. The pipe area
to be coated is first heated by the Pipe Induction Heating Assembly.
Heating coils made for a specific pipe size must be changed out as
the pipe size changes. Preset values for voltage and current are
used to heat the pipe for a given period of time. The temperature
must be correct to gel the powder when it is applied. With the pipe
hot, the heating coil assembly is removed. The Pipe Induction Heating
Assembly is moved and replaced with the Powder Applicator Unit over
the heated area. This unit is hinged, also, to encircle the pipe.
As powder is being blown onto the heated surface, the applicator
travels forward and reverse around the pipe, making sure all the
pattern area is completely coated. When powder coating is done, the
powder spray is shut off, and the applicator removed from about the
pipe. Typical system consists of the following: Diesel-Generator Unit
Induction Heating Coil
Powder Box
Powder Applicator Unit |
|
|
|
|
|
| |
 |
|
| |
This plant applies primer and coal
tar enamel coating onto pipe for the purpose of anti-corrosion protection.
In most cases the pipe surface is cleaned by shot blasting prior
to coating. After the shot blasting of the pipe two different configurations
are possible. The basic difference is the position of the primer
station. With the first configuration the pipe surface can not be
inspected. After the shot blast machine is a small conveyor that
conveys the pipe toward a pipe carriage. Between the conveyor and
carriage, the pipe surface will be primed. In the second configuration
an outgoing conveyor, after the shot blast machine, transports
the pipe towards outgoing skidways. As usual the pipe is lifted from
the conveyor by padded pipe ejection units. The pipe can be blown-out,
inspected, and grind. If the pipe surface has not been cleaned
properly, it can be transported to the in-coming shot blast machine
conveyor by ENDO conveyor modules. After inspection, the pipe will
be moved to the primer station. After priming, the weld seam can
be coated to make sure enough coating covers this area. Then the
pipe is lowered onto the incoming coating conveyor which transports
the pipe through the coating area. After coating, the pipe is cooled
down in a cooling tunnel. Pipe ejection arm kicks the pipe out
of the outgoing conveyor. External Coal Tar Enamel Coating Plant
consist of: Incoming Skidways
Seam Coating Applicator Machine (Optional)
Intermediate Pipe Skidways
(Optional)
Feed-in and Lower-in Units
Incoming Skew Conveyor
Enclosed Coating Pan
Coating Hood, Weirs and Exhaust Blower
Tension Wrap Stands
Double Coating Pump Unit
Manual Cutback Unit
Smoke Scrubber System
In-line High-voltage Holiday Detector
Coating Material Melting
System
Dope Chopper Machine with Barrel Skinner (Stationary)
Loading Conveyor
for Kettles
Cooling Skew Conveyor
Pipe Cooling Tunnel
Cooling System
Outgoing Skew Conveyor
Padded Pipe Ejection Units
Outgoing Skidways (Optional)
Pipe End Cleaning and Cutback Beveling
Machine (Optional)
Outgoing Skidways (Optional)
Electric Hydraulic Power Unit
Control Console |
|
|
|
|
|
| |
 |
|
| |
This coating system is capable
of applying Multi-Layer Coating consisting of a Fusion Bonded Epoxy
Layer, an Adhesive tie layer and multiple Polyethylene Layers onto
the pipe. Also, a single layer of Fusion Bonded Epoxy can be applied.
The Fusion Bonded Epoxy Layer is applied for the purpose of anti-corrosion
protection. The adhesive layer sticks the Polyethylene Layer to
the Fusion Bonded Epoxy Layer. The Polyethylene Layer protects the
Fusion Bonded Epoxy Layer against impact during transportation and
pipe handling the pipe. Pipes are placed on the incoming skewed roller
conveyor and transported to the heating system where the pipe will
be preheated to the appropriate temperature. Using intermediate
conveyors, the pipe will then be transported through the coating
application area where the 3-layer coating can be applied. Pipes
will be separated immediately after coating and will then be cooled
down on the cooling conveyor with a controlled volume of recirculating
water. The outgoing conveyor will move the pipe to the ejection arms
for ejection onto the skidways for inspection and end-cleaning. The
components that are supplied for the application of the coating
materials is designed to be used to apply multi-layer type of coating
system in accordance with the coating material manufacturers and
Buyer’s
specification. Typical System consists of the following: Incoming Skidways
Feed-in and Lower-in Units
Incoming Skew Conveyor
Vacuum Dust Removal System
High Pressure Water Wash Unit
Inorganic Chromate Application System
Pipe Heating System
Intermediate Conveyor (between coil and coating
section)
Fusion Epoxy Powder Application and Reclaim System
Copolymer Extrusion
System
PE/PP Extrusion System
Water Cooled Pressure Roller with Weld Seam
Sensor
Control and Monitoring console for Coating Systems
In-Line High-voltage
Holiday Detector
Cooling Skew Conveyor
Pipe Cooling Tunnel
Outer Cooling System
Outgoing Skew Conveyor
Padded Pipe Ejection Units
Electric Hydraulic Power Unit
Intermediate Padded Pipe Skidways
Pipe End Cleaning and Cutback Beveling
Machine
Outgoing Skidways
Components for Quality Control and Inspection Equipment
20 foot Tool
Container |
|
|
|
|
|
| |
 |
|
| |
This machine is designed to batch
cement, and apply a heavy coat of concrete to the outside of anti-corrosion
protected steel pipe to provide negative buoyancy to the pipe for
offshore pipelines or river crossings. The weight coating machine
uses a concrete batching plant to precisely measure aggregate and
cement to produce any desired mixture accurately. An automatic
moisture-sensing unit is employed to determine the amount of water
required and in turn automatically dispenses the correct amount.
The plant is equipped to batch two (2) different aggregates in addition
to cement. Each ingredient is automatically weighed and held until
mixer is ready for a new batch. After material is mixed, it is taken
up the transfer conveyor to the receiving hopper. Material is metered
out of holding hopper onto a metering conveyor, which shapes the
wet concrete and in turn delivers material onto a high speed slinger
belt. Prior to coating, the pipe may need special preparation, depending
on coating type wire brushes are used to give the pipe a rough surface
to increase surface adhesion and for a certain percentage anode rings
need to be installed. Pipe is then loaded into pipe support carriages
with heavy-duty pipe loaders. The support carriages are designed
to rotate the pipe, and traversed in front of the application head
at a controlled rate. Pipe is sprayed with water just prior to applying
concrete to increase the bond between the corrosion coating and concrete.
The slinger head propels pre-mixed concrete onto the pipe, at a
high velocity to promote coating adhesion. A wire mesh is simultaneously
wrapped around the pipe to reinforce the concrete. A curing compound
is also sprayed on after concrete application to accelerate the
curing time of concrete. After the pipe is coated, the pipe is removed
with heavy-duty pipe unloaders and placed onto the weigh scales.
Finally the pipe is taken to the storage area for final curing, in
some cases steam curing is required depending on the environmental
conditions. Note: Production will vary depending on customer specifications
in relation to thickness and the amount on anodes required, increased
production is attainable if the optional pipe loaders / unloaders
are purchased. Typical system consists of the following: Concrete Application Machine
Wire Feed System
Concrete Reclaim System
Curing Compound Unit
Control Console
Pipe Carriages
Pipe Unloader/Loader Carriages
Weigh Station
Hydraulic Power Unit
Air Compressor
Automatic Concrete Batching Plant |
|
|
|
|
|
| |
 |
|
| |
This system is designed to clean the internal pipe surface, in preparation for internal coating procedures. Degree of cleanliness is controlled by the speed of the internal blast boom transferred through the pipe being prepared. This system is used to clean pipes with a diameter of 4" – 24" range.
PROCESS
Pipes are separated by a pipe positioning apparatus. After that, they will be picked up by the transfer unit and lowered onto the pipe turning rollers.
The boom carriage will drive internal lances into the pipe and on their way back grid will be transported through the lances and nozzles in order to clean the pipe surface. After the cleaning operation, the pipes are transported by the transfer unit onto outgoing skidways.
Typical system consists of the following:
Powered boom carriage
Internal lances
Pipe transfer unit
Pipe turning roller units
Blast room enclosure
Dust collector
Abrasive reclaim belt system
Abrasive cleaning and handling system
Control console
|
|
|
|
|
|
| |
 |
|
| |
This system is designed to apply a suitable spray coating, primer, or epoxy to the abrasively cleaned internal surface of the pipe. This equipment is recommended for API, NAPCA, NACE, and most other international coating specifications similar to the A/M coating specifications.
PROCESS
After pipe has been abrasively cleaned and all residual dust and grit has been removed, the pipe is transferred to the pipe turning roller unit. The turning roller unit rotates the pipe as the spray boom is inserted into the pipe until the spray head is located outside the opposite end of the pipe. As the boom is reversed, the spraying process starts. The turning roller continues to rotate the pipe until the spraying process is complete. All liquid epoxy spray equipment, such as pumps, tanks, hoses, and electric drives are mounted on the spray boom carriage.
The boom carriage is moved on track rails capable of traversing the full length of pipe. There two adjustable collector carriages c/w extraction fans to extract the hazardous fumes that are emitted during the spraying process. The hazardous fumes are ventilated out of the building via ducting suitable to take away from the work area.
Typical system consists of the following:
- Powered boom carriage with paint preparation equipment
- Internal boom with spray head
- Pipe turning roller units
- Paint reclaim collector carriages
- Hydraulic power unit
- Control console
|
|
|
|
|
|
| |
 |
|
| |
The Internal Cement Mortar Lining Machine is designed to apply internal mortar linings in steel pipe. Internal cement mortar lining is normally used for water service application. Recommended for AWWA Standard C205-89 coating specifications.
PROCESS
Pipes are fed onto the rotation belts. A carriage drives the cement application boom into the pipe. On its way back, the applicator head applies the cement. After the coating application, the rotation belts rotate the pipe.
Typical system consists of the following:
- Skidways
- Pipe Index Rollers
- Lower-In Units
- Pipe Rotation Units
- Boom Carriage
- Internal Boom and Applicator Head
- Cement Batch Plant
- Belt Conveyor
- Air Compressor
- Control Console
|
|
|
| |
|
|
| |
Back to Top |
|